Brad's blog is that of Hammond-Henry Hospital's CEO, Brad Solberg. Here is where you can find the latest information on construction progress and exciting changes underway at Hammond-Henry Hospital. Check back often for news, photos and up-to-date information.
By Brad Solberg on 6/8/2011 9:51 AM
Open house for HHH Long Term Care Living Center held on Sunday, June 5.  The turnout was huge!
By Brad Solberg on 4/29/2011 3:02 PM
Making way for the third operating room, as the completion of long term care draws near.
By Brad Solberg on 4/16/2011 12:14 PM
The Illinois Department of Public Health has granted occupancy to our new endoscopy suite.
By Brad Solberg on 4/5/2011 3:34 PM
The new endoscopy suite is ready for inspection.
By Brad Solberg on 2/26/2011 1:07 PM
The new endoscopic suite is ready for inspection, and the long term care addition is ahead of schedule.
By Brad Solberg on 2/11/2011 7:46 AM
Work continues- even through blizzards.    
By Brad Solberg on 1/27/2011 1:54 PM
The new endoscopy suite is less than a month away!
By Brad Solberg on 1/17/2011 9:36 AM
The south service building is beginning to take shape!
By Brad Solberg on 1/6/2011 1:11 PM
The concrete floor on the second story of the south service building was poured this week.
By Brad Solberg on 12/21/2010 8:50 AM
If the mild, dry weather could have held out for another two weeks in November, the south service building would have been enclosed.  Nonetheless, work continues to accomplish that task despite the challenges with the weather.  The concrete floor was poured in the south service building ten days ago and has cured well.  The next step is to install the roof on the building.  Once installed, temporary plastic curtains can enclose the second floor allowing for the final concrete pour for the second floor.  Plans are to complete the roof by the end of the month, with the floor to be completed shortly thereafter.

In the long term care building, significant progress continues to be made with HVAC, electrical, fire sprinkler installations moving along well.  With this building being weather-tight the trades are working diligently.  Rooms are beginning to take shape with drywall installation underway in some areas.